The Flexibility Matrix
An important aspect of the project manager’s role is the appropriate balancing of trade-offs among the primary project constraints. In most cases this means determining priorities among schedule, scope and resources. The relative importance of these should be defined unambiguously by the project sponsor and then reflected by the PM in a matrix:

Forcing clarity on project constraints and priorities
In the example above, schedule is deemed to have the least flexibility, meaning that everything possible shall be done to meet the target completion date, even if scope has to be compromised in some way, or more preferably, by adding resources to expedite the schedule. It is important to state WHY a particular constraint is either least, moderately, or most flexible, according to the sponsor’s priorities, with guidance on the relative limits of flexibility (so no blank cheques).
This little tool is invaluable to the project manager during both planning (in ensuring the right focus in optimizing the project plan before baselining) and execution (in guiding both the tracking effort and corrective action in the event the project deviates from the plan).
While the relative priorities can be changed by management as desired, a simple rule must be followed to prevent insistence that everything be least flexible – only ONE check allowed per column and ONE check allowed per row.