Posts Tagged ‘Sponsorship’

PostHeaderIcon Six First Steps for the Project Manager

How you start determines how you finish

Time is sometimes lost at project startup with lots of talk but not much action (the “fuzzy front end”). Contrast this with the intensity of effort expended by the team near the end of the project – rushing to meet a looming deadline – and the need for some up-front structure and focus becomes clear.

Each project manager may have their own take on this, (and the actual first steps will be somewhat dependent on the particular situation) but these six should be at the front end of any list:

1 – Read the Business Case

If it doesn’t exist, get one done. There’s no point embarking on a project if the rationale for WHY we’re doing the project and WHO it’s for hasn’t been clearly laid out and signed off. If it does exist, identify who developed it, who was consulted and who approved it. Lastly, is it still current? Has anything changed in the environment that might affect realization of the anticipated benefits?

2 – Identify the Key Stakeholders

Who benefits from the project? Who can influence the outcomes and who might be impacted by them? The business case should be a guide but performing a thorough stakeholder analysis is essential before the next step is finished. Identify the project sponsor and set up an early “mind-meld” meeting to establish Sponsor-PM rapport (see Eight Questions to Ask Your Sponsor).

3 – Determine the Requirements

What does the customer actually need? What do other key stakeholders want? What has to be delivered in order to achieve the target benefits? Detailed requirements gathering and analysis may need to occur later as part of the project scope but the high-level needs at least should be established here. Determine what constraints will influence how the requirements might be met – these will impact project scope, quality, schedule, costs and resources.

4 – Identify Similar Projects

Has anything similar been done before? If so, what lessons were learned from that project (see Three Agenda Items for a Lessons Learned Review). Is there anything similar, or somehow related, going on currently? If yes, might there be potential overlap or dependencies? Can any artifacts from similar projects (e.g. plans, actuals, risk data) be re-used?

5 – Identify the Core Team Members

Which functions need to be involved to define and generate the project deliverables? Who specifically should represent those functions in the project? Who do you need on board to help generate a complete, reliable plan? Who should oversee the various workstreams? Limit the core team to no more than 8 people to promote efficient meetings and decision making.

6 – Create a Project Objective Statement

WHAT will be done, by WHEN and for HOW MUCH? The project should have a concise, over-arching declaration of intent (see The Project Objective Statement). Doing this (ideally as the first activity involving the core team) quickly shifts the focus away from the strategic (business case) and onto the tactical aspects of the project; it also helps to highlight potential issues early on, and ensures high level clarity and alignment as a precursor to elaborating the details of the project plan. Validate the POS with the Sponsor.

Begin with the End in Mind

The step numbering here indicates only the general flow – it is not a prescriptive project startup sequence as oftentimes a degree of iteration will occur among the six before they can all be checked off as ‘done’. These first steps neatly embody the adage “Begin with the end in mind” and initiate a response to the Five Laws (see The Five Laws of Effective Project Management).

PostHeaderIcon The Flexibility Matrix

An important aspect of the project manager’s role is the appropriate balancing of trade-offs among the primary project constraints. In most cases this means determining priorities among schedule, scope and resources. The relative importance of these should be defined unambiguously by the project sponsor and then reflected by the PM in a matrix:

Forcing clarity on project constraints and priorities

Forcing clarity on project constraints and priorities

In the example above, schedule is deemed to have the least flexibility, meaning that everything possible shall be done to meet the target completion date, even if scope has to be compromised in some way, or more preferably, by adding resources to expedite the schedule. It is important to state WHY a particular constraint is either least, moderately, or most flexible, according to the sponsor’s priorities, with guidance on the relative limits of flexibility (so no blank cheques).

This little tool is invaluable to the project manager during both planning (in ensuring the right focus in optimizing the project plan before baselining) and execution (in guiding both the tracking effort and corrective action in the event the project deviates from the plan).

While the relative priorities can be changed by management as desired, a simple rule must be followed to prevent insistence that everything be least flexible – only ONE check allowed per column and ONE check allowed per row.

PostHeaderIcon Eight Questions to ask your Project Sponsor

This might have been alternatively titled “Questions we are Occasionally Afraid to Ask”. Here’s the situation:

You’ve been appointed to project manage a new initiative. You know that effective project sponsorship is a critical success factor and so you set up a meeting with the project sponsor.  You want to be sure you’re starting out with the right kind of backing. The sponsor wants to discuss the budget (or maybe golf) but first, you have some big questions you need answers to…

1 – Do you understand your role?
Its a fact – many project managers I meet complain that their sponsor has little idea about their role and responsibilities. You may need to help them out here.

2 – Do you know what you want?
There’s not much more frustrating than a sponsor who isn’t sure about what should or should not be included in the project. A fuzzy sponsor means you could be in for a long road trip of about-turns – do, undo, redo, …

3 – Can I count on your support?
Or more specifically – will you truly champion our project? This means advocating the project at higher levels, helping maintain visibility and interest in the project with key stakeholders, providing adequate funding and obtaining resources.

4 – Will you be available?
No doubt about it, sponsors are typically busy executives. This means their time is limited and they may be hierarchically or geographically remote. You DO need those face-to-face meetings. Lock them into their calendar.

5 – Can you give me clear priorities?
What are the primary project objectives? Which is least flexible – schedule, scope or resources? (Hint to sponsor- you can choose only one). Which is most flexible? Why?

6 – Do you understand that project management is a discipline?
In pushing to ‘just get it done’, countless projects ignore the importance of proper planning and systematic tracking… and pay a high price. A sponsor who doesn’t appreciate this means we’re already in trouble.

7 – Do you know what a solid project plan looks like?
The sponsor has to approve the plan that lays out what will actually be done- so it might make sense to ensure they actually have an understanding of what a good plan looks like. If necessary, give them a Plan Review checklist and an ‘Executive Briefing on Tactical Planning’ (so they know a WBS from a critical path).

8 – Will you inspect what you expect?
Not much point in a sponsor’s list of expectations if the relevant questions are never going to be asked. Generating information, reports and updates that don’t get reviewed is a fast track to morale hits and trust breakdown.

If the sponsor answered these questions correctly, you’re likely to be in good shape. (Hint for sponsors- the correct answer is “Yes” to all questions). If not, then you just identified some additional risks to the project…